Construction Updates - March 2020

- For A Block, Roofing is completed till the 12th floor. Pillaring work is completed for the

13th floor and roofing work is in progress. Brickwork is completed till the 6th floor and is

in progress on the 7th floor. Plastering work is finished till the 5th floor. 1st coat of wall

putty is completed till 5th floor, Plumbing and electrical works are started.

- For B Block, Roofing is completed till 12th floor and Pillaring is in progress for 13th

floor. Brick work is completed till 6th floor and is in progress in 7th floor.

- For C Block, Roofing is completed till 6th floor and Pillaring is in progress for 7th floor.

Brick work is completed till 5th floor and is in progress in 6th floor.

- For D Block, Roofing is completed in 5nd floor and pillaring is in progress in 6th floor.

Brick work is completed till 1st floor and is in progress in 2nd floor.

- Model flat is now “OPEN” for your viewing.